Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2001 |
Principal Product | Roofing fasteners |
NAICS | n/a |
SIC | 3451 - Screw Machine Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 230 |
Plant Area (Sq.Ft.) | 76,000 |
Annual Production | 1,000,000,000 Pieces |
Production Hrs. Annual | 7,500 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $238,882 | 4,034,880 | kWh | $0.06 |
Electricity Demand | $97,295 | 8,824 | kW-months/year | $11.03 |
Electricity Fees | $27,589 | - | $ | - |
Natural Gas | $90,242 | 11,523 | MMBtu | $7.83 |
TOTAL ENERGY COSTS | $454,008 | |||
RECOMMENDED SAVINGS* | $36,240 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,280 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $23,000 Cost: $10,000 |
- | - | - | - | $(-2,500) | (-309) | $25,500 | 28,500 |
- - kWh |
- - kW-months/year |
$(-2,500) (-309) MMBtu |
$25,500 28,500 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $5,800 Cost: $360 |
$4,300 | 72,000 | $1,500 | 115 | - | - | - | - |
$4,300 72,000 kWh |
$1,500 115 kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,800 Cost: $15,000 |
$4,800 | 79,700 | - | - | - | - | - | - |
$4,800 79,700 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $2,160 Cost: $12,000 |
$2,800 | 46,900 | $960 | 75 | $(-1,600) | (-200) | - | - |
$2,800 46,900 kWh |
$960 75 kW-months/year |
$(-1,600) (-200) MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $480 Cost: $200 |
$480 | 8,100 | - | - | - | - | - | - |
$480 8,100 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $36,240 Cost: $37,560 |
$12,380 | 206,700 | $2,460 | 190 | $(-4,100) | (-509) | $25,500 | 28,500 | $12,380 206,700 kWh |
$2,460 190 kW-months/year |
$(-4,100) (-509) MMBtu |
$25,500 28,500 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,280 Cost: $560 |
$4,780 | 80,100 | $1,500 | 115 | - | - | - | - | $4,780 80,100 kWh |
$1,500 115 kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) |