IAC Assessment: MA0496
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0496
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2001
Principal Product Easter White Pine Boards
NAICS n/a
SIC 2421 - Sawmills And Planing Mills, General
Sales $5,000,000-$10,000,000
# of Employees 18
Plant Area (Sq.Ft.) 46,450
Annual Production 5,000 Thousand Feet
Production Hrs. Annual 2,140
Location (State) NH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $63,196 721,366 kWh $0.09
Electricity Demand $8,912 4,959 kW-months/year $1.80
Electricity Fees $2,889 - $ -
Fuel Oil #2 $33,307 4,276 MMBtu $7.79
TOTAL ENERGY COSTS $108,304
RECOMMENDED SAVINGS* $27,547 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,209
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #2 Administrative Changes Electricity Usage Fuel Oil #2 Administrative Changes
$ kWh $ MMBtu $ $
01: 2.4311 RECOVER MECHANICAL ENERGY Savings:
$9,000
Cost:
$40,000
$4,000 51,252 - - $5,000 - $4,000
51,252
kWh
-
-
MMBtu
$5,000
-
$
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$6,447
Cost:
$17,000
- - $6,447 1,071 - - -
-
kWh
$6,447
1,071
MMBtu
-
-
$
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,736
Cost:
$23,650
$4,736 60,713 - - - - $4,736
60,713
kWh
-
-
MMBtu
-
-
$
04: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING Savings:
$3,155
Cost:
$50,000
- - $3,155 524 - - -
-
kWh
$3,155
524
MMBtu
-
-
$
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,200
Cost:
-
$2,200 28,206 - - - - $2,200
28,206
kWh
-
-
MMBtu
-
-
$
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,090
Cost:
$1,100
- - $1,090 181 - - -
-
kWh
$1,090
181
MMBtu
-
-
$
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$846
Cost:
$3,000
$846 10,840 - - - - $846
10,840
kWh
-
-
MMBtu
-
-
$
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$73
Cost:
$400
$73 931 - - - - $73
931
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$27,547
Cost:
$135,150
$11,855 151,942 $10,692 1,776 $5,000 - $11,855
151,942
kWh
$10,692
1,776
MMBtu
$5,000
-
$
TOTAL IMPLEMENTED Savings:
$13,209
Cost:
$44,500
$7,119 91,229 $1,090 181 $5,000 - $7,119
91,229
kWh
$1,090
181
MMBtu
$5,000
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Fuel Oil #2 Administrative Changes Electricity Usage Fuel Oil #2 Administrative Changes