IAC Assessment: MA0542
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2003
Principal Product Business forms
NAICS 326112 - Plastics Packaging Film and Sheet (including Laminated) Manufacturing
SIC 2671 - Paper Coated & Laminated, Packaging
Sales $10,000,000-$50,000,000
# of Employees 150
Plant Area (Sq.Ft.) 146,000
Annual Production 52,000,000 Pounds
Production Hrs. Annual 6,200
Location (State) NH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $849,046 10,953,500 kWh $0.08
Electricity Demand $143,159 24,547 kW-months/year $5.83
Electricity Fees $5,093 - $ -
Fuel Oil #2 $119,273 18,694 MMBtu $6.38
TOTAL ENERGY COSTS $1,116,571
RECOMMENDED SAVINGS* $54,177 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $15,080
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Fuel Oil #2 Electricity Usage Electricity Demand Fuel Oil #2
$ kWh $ kW-months/year $ MMBtu
01: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$14,636
Cost:
$22,869
- - $14,636 2,100 - - -
-
kWh
$14,636
2,100
kW-months/year
-
-
MMBtu
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$13,600
Cost:
$21,400
$13,600 185,400 - - - - $13,600
185,400
kWh
-
-
kW-months/year
-
-
MMBtu
03: 2.7314 REDUCE VENTILATION AIR Savings:
$9,202
Cost:
$3,400
$5,738 76,500 - - $3,464 543 $5,738
76,500
kWh
-
-
kW-months/year
$3,464
543
MMBtu
04: 2.2691 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS Savings:
$8,465
Cost:
-
$8,465 110,800 - - - - $8,465
110,800
kWh
-
-
kW-months/year
-
-
MMBtu
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$4,383
Cost:
-
$4,383 49,900 - - - - $4,383
49,900
kWh
-
-
kW-months/year
-
-
MMBtu
06: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$2,232
Cost:
$500
- - - - $2,232 351 -
-
kWh
-
-
kW-months/year
$2,232
351
MMBtu
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,659
Cost:
$3,400
$1,659 18,900 - - - - $1,659
18,900
kWh
-
-
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$54,177
Cost:
$51,569
$33,845 441,500 $14,636 2,100 $5,696 894 $33,845
441,500
kWh
$14,636
2,100
kW-months/year
$5,696
894
MMBtu
TOTAL IMPLEMENTED Savings:
$15,080
Cost:
$500
$12,848 160,700 - - $2,232 351 $12,848
160,700
kWh
-
-
kW-months/year
$2,232
351
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Fuel Oil #2 Electricity Usage Electricity Demand Fuel Oil #2