Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2004 |
Principal Product | Aluminum anodizing |
NAICS | 332813 - Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471 - Plating And Polishing |
Sales | $5,000,000-$10,000,000 |
# of Employees | 85 |
Plant Area (Sq.Ft.) | 25,000 |
Annual Production | 1,312,500 Pieces |
Production Hrs. Annual | 6,552 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $120,729 | 1,944,960 | kWh | $0.06 |
Electricity Demand | $50,282 | 5,972 | kW-months/year | $8.42 |
Natural Gas | $112,000 | 13,000 | MMBtu | $8.62 |
Fuel Oil #2 | $33,215 | 4,900 | MMBtu | $6.78 |
TOTAL ENERGY COSTS | $316,226 | |||
RECOMMENDED SAVINGS* | $40,006 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,665 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7314 REDUCE VENTILATION AIR |
Savings: $13,881 Cost: $4,244 |
$3,614 | 57,800 | - | - | $10,267 | 1,619 |
$3,614 57,800 kWh |
- - kW-months/year |
$10,267 1,619 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $9,950 Cost: $4,150 |
$9,950 | 159,200 | - | - | - | - |
$9,950 159,200 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $7,609 Cost: $19,680 |
- | - | - | - | $7,609 | 1,087 |
- - kWh |
- - kW-months/year |
$7,609 1,087 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,665 Cost: $1,100 |
- | - | - | - | $4,665 | 735 |
- - kWh |
- - kW-months/year |
$4,665 735 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,528 Cost: $1,625 |
- | - | - | - | $1,528 | 218 |
- - kWh |
- - kW-months/year |
$1,528 218 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $699 Cost: $3,574 |
$699 | 11,200 | - | - | - | - |
$699 11,200 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $653 Cost: $200 |
$537 | 7,900 | $116 | 14 | - | - |
$537 7,900 kWh |
$116 14 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7314 REDUCE VENTILATION AIR |
Savings: $607 Cost: $1,831 |
- | - | - | - | $607 | 77 |
- - kWh |
- - kW-months/year |
$607 77 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $414 Cost: $200 |
$340 | 5,000 | $74 | 9 | - | - |
$340 5,000 kWh |
$74 9 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,006 Cost: $36,604 |
$15,140 | 241,100 | $190 | 23 | $24,676 | 3,736 | $15,140 241,100 kWh |
$190 23 kW-months/year |
$24,676 3,736 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,665 Cost: $1,100 |
- | - | - | - | $4,665 | 735 | - - kWh |
- - kW-months/year |
$4,665 735 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |