IAC Assessment: MA0569
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0569
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2005
Principal Product Loudromat
NAICS 314999 - All Other Miscellaneous Textile Product Mills
SIC 2299 - Textile Goods, Nec
Sales $10,000,000-$50,000,000
# of Employees 48
Plant Area (Sq.Ft.) 45,000
Annual Production 1,040 Tons
Production Hrs. Annual 6,240
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $67,537 850,530 kWh $0.08
Electricity Demand $55,193 3,116 kW-months/year $17.71
Electricity Fees $1,721 - $ -
Natural Gas $54,230 4,269 MMBtu $12.70
Fuel Oil #6 $131,725 22,074 MMBtu $5.97
TOTAL ENERGY COSTS $310,406
RECOMMENDED SAVINGS* $70,412 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,141
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Fuel Oil #6 Electricity Usage Electricity Demand Natural Gas Fuel Oil #6
$ kWh $ kW-months/year $ MMBtu $ MMBtu
01: 2.3416 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST Savings:
$67,271
Cost:
$331,800
$50,734 660,600 $62,760 3,000 $(-66,943) (-6,930) $20,720 3,616 $50,734
660,600
kWh
$62,760
3,000
kW-months/year
$(-66,943)
(-6,930)
MMBtu
$20,720
3,616
MMBtu
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,234
Cost:
$7,312
$1,234 15,700 - - - - - - $1,234
15,700
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
MMBtu
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,082
Cost:
$494
- - - - - - $1,082 188 -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,082
188
MMBtu
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$825
Cost:
$5,248
$825 10,500 - - - - - - $825
10,500
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$70,412
Cost:
$344,854
$52,793 686,800 $62,760 3,000 $(-66,943) (-6,930) $21,802 3,804 $52,793
686,800
kWh
$62,760
3,000
kW-months/year
$(-66,943)
(-6,930)
MMBtu
$21,802
3,804
MMBtu
TOTAL IMPLEMENTED Savings:
$3,141
Cost:
$13,054
$2,059 26,200 - - - - $1,082 188 $2,059
26,200
kWh
-
-
kW-months/year
-
-
MMBtu
$1,082
188
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ MMBtu
Electricity Usage Electricity Demand Natural Gas Fuel Oil #6 Electricity Usage Electricity Demand Natural Gas Fuel Oil #6