Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2006 |
Principal Product | Coated fabrics and foams |
NAICS | 313310 - Textile and Fabric Finishing Mills |
SIC | 2295 - Coated Fabrics, Not Rubberized |
Sales | $100,000,000-$500,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 300,000 |
Annual Production | 30,600 Thousand Feet |
Production Hrs. Annual | 5,616 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,181,102 | 13,419,840 | kWh | $0.09 |
Electricity Demand | $532,825 | 38,341 | kW-months/year | $13.90 |
Electricity Fees | $9,168 | - | $ | - |
Natural Gas | $413,073 | 46,407 | MMBtu | $8.90 |
TOTAL ENERGY COSTS | $2,136,168 | |||
RECOMMENDED SAVINGS* | $153,120 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $38,943 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $89,422 Cost: $172,300 |
$(-9,495) | (-111,700) | - | - | $98,917 | 11,164 |
$(-9,495) (-111,700) kWh |
- - kW-months/year |
$98,917 11,164 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $20,495 Cost: $3,700 |
$15,200 | 178,840 | $5,295 | 375 | - | - |
$15,200 178,840 kWh |
$5,295 375 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2443 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR |
Savings: $17,205 Cost: $10,250 |
- | - | - | - | $17,205 | 1,755 |
- - kWh |
- - kW-months/year |
$17,205 1,755 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $10,010 Cost: $5,280 |
- | - | - | - | $10,010 | 1,140 |
- - kWh |
- - kW-months/year |
$10,010 1,140 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $5,780 Cost: $12,325 |
$5,780 | 68,000 | - | - | - | - |
$5,780 68,000 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT |
Savings: $4,260 Cost: $1,190 |
- | - | - | - | $4,260 | 485 |
- - kWh |
- - kW-months/year |
$4,260 485 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,051 Cost: $7,865 |
$3,051 | 35,900 | - | - | - | - |
$3,051 35,900 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.5123 REDUCE FLUID FLOW RATES |
Savings: $2,270 Cost: $600 |
$1,480 | 17,450 | $790 | 56 | - | - |
$1,480 17,450 kWh |
$790 56 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $627 Cost: $600 |
$627 | 7,374 | - | - | - | - |
$627 7,374 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $153,120 Cost: $214,110 |
$16,643 | 195,864 | $6,085 | 431 | $130,392 | 14,544 | $16,643 195,864 kWh |
$6,085 431 kW-months/year |
$130,392 14,544 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $38,943 Cost: $36,920 |
$10,938 | 128,724 | $790 | 56 | $27,215 | 2,895 | $10,938 128,724 kWh |
$790 56 kW-months/year |
$27,215 2,895 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |