Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2010 |
Principal Product | Surface Finishing by Cut-Wire Peening and Vibratory Milling of Turbine A |
NAICS | 332811 - Metal Heat Treating |
SIC | 3398 - Metal Heat Treating |
Sales | $1,000,000-$5,000,000 |
# of Employees | 30 |
Plant Area (Sq.Ft.) | 13,000 |
Annual Production | 216,000 Pieces |
Production Hrs. Annual | 7,488 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $136,397 | 1,429,733 | kWh | $0.10 |
Electricity Demand | $38,109 | 4,276 | kW-months/year | $8.91 |
Electricity Fees | $(-2,882) | - | $ | - |
Natural Gas | $1,008 | 20 | MMBtu | $50.40 |
TOTAL ENERGY COSTS | $172,632 | |||
RECOMMENDED SAVINGS* | $24,734 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,975 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $15,680 Cost: $58,600 |
$15,680 | 164,361 | - | - |
$15,680 164,361 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $3,642 Cost: $18,330 |
$3,642 | 36,299 | - | - |
$3,642 36,299 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,625 Cost: $2,000 |
$3,285 | 34,444 | $(-1,660) | (-130) |
$3,285 34,444 kWh |
$(-1,660) (-130) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,470 Cost: $200 |
$1,470 | 15,400 | - | - |
$1,470 15,400 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,134 Cost: $3,150 |
$1,134 | 11,886 | - | - |
$1,134 11,886 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,028 Cost: $480 |
$1,028 | 10,782 | - | - |
$1,028 10,782 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $155 Cost: $180 |
$155 | 1,617 | - | - |
$155 1,617 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $24,734 Cost: $82,940 |
$26,394 | 274,789 | $(-1,660) | (-130) | $26,394 274,789 kWh |
$(-1,660) (-130) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,975 Cost: $77,790 |
$21,975 | 228,459 | - | - | $21,975 228,459 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |