Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2011 |
Principal Product | Extruded plastic |
NAICS | 325991 - Custom Compounding of Purchased Resins |
SIC | 3087 - Custom Compound Purchased Resins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 67 |
Plant Area (Sq.Ft.) | 44,000 |
Annual Production | 325 Tons |
Production Hrs. Annual | 6,240 |
Location (State) | CT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $193,738 | 1,578,960 | kWh | $0.12 |
Electricity Demand | $49,371 | 3,974 | kW-months/year | $12.42 |
Electricity Fees | $4,800 | - | $ | - |
Natural Gas | $37,540 | 2,931 | MMBtu | $12.81 |
TOTAL ENERGY COSTS | $285,449 | |||
RECOMMENDED SAVINGS* | $9,539 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,325 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7314 REDUCE VENTILATION AIR |
Savings: $6,162 Cost: $9,261 |
$4,709 | 38,384 | $1,453 | 183 |
$4,709 38,384 kWh |
$1,453 183 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4237 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING |
Savings: $1,294 Cost: $1,220 |
$1,294 | 10,548 | - | - |
$1,294 10,548 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,163 Cost: $1,265 |
$1,163 | 9,480 | - | - |
$1,163 9,480 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $768 Cost: $300 |
$768 | 6,262 | - | - |
$768 6,262 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $152 Cost: $80 |
$152 | 1,236 | - | - |
$152 1,236 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $9,539 Cost: $12,126 |
$8,086 | 65,910 | $1,453 | 183 | $8,086 65,910 kWh |
$1,453 183 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,325 Cost: $10,526 |
$5,872 | 47,864 | $1,453 | 183 | $5,872 47,864 kWh |
$1,453 183 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |