Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2014 |
Principal Product | Standard and Special cuttingTools |
NAICS | 333517 - Machine Tool Manufacturing |
SIC | 3541 - Machine Tools, Metal Cutting Types |
Sales | $5,000,000-$10,000,000 |
# of Employees | 44 |
Plant Area (Sq.Ft.) | 55,000 |
Annual Production | 4,160 Pieces |
Production Hrs. Annual | 4,080 |
Location (State) | VT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $81,470 | 1,140,585 | kWh | $0.07 |
Electricity Demand | $57,350 | 6,681 | kW-months/year | $8.58 |
Electricity Fees | $23,366 | - | $ | - |
LPG | $26,391 | 1,507 | MMBtu | $17.51 |
Fuel Oil #4 | $41,251 | 1,874 | MMBtu | $22.01 |
TOTAL ENERGY COSTS | $254,930 | |||
RECOMMENDED SAVINGS* | $29,890 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $29,566 |
#|Description |
Savings Cost |
Status | Electricity Usage | LPG | Fuel Oil #4 | Water Disposal | Electricity Usage | LPG | Fuel Oil #4 | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) |
Savings: $16,512 Cost: $25,775 |
- | - | $(-6,708) | (-383) | $23,220 | 1,060 | - | - |
- - kWh |
$(-6,708) (-383) MMBtu |
$23,220 1,060 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1224 REPLACE BOILER |
Savings: $10,114 Cost: $30,450 |
- | - | $(-30,916) | (-1,765) | $41,030 | 1,873 | - | - |
- - kWh |
$(-30,916) (-1,765) MMBtu |
$41,030 1,873 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD |
Savings: $2,940 Cost: $6,500 |
$(-1,636) | (-21,812) | - | - | - | - | $4,576 | 933 |
$(-1,636) (-21,812) kWh |
- - MMBtu |
- - MMBtu |
$4,576 933 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $324 Cost: $350 |
- | - | - | - | $324 | 15 | - | - |
- - kWh |
- - MMBtu |
$324 15 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,890 Cost: $63,075 |
$(-1,636) | (-21,812) | $(-37,624) | (-2,148) | $64,574 | 2,948 | $4,576 | 933 | $(-1,636) (-21,812) kWh |
$(-37,624) (-2,148) MMBtu |
$64,574 2,948 MMBtu |
$4,576 933 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $29,566 Cost: $62,725 |
$(-1,636) | (-21,812) | $(-37,624) | (-2,148) | $64,250 | 2,933 | $4,576 | 933 | $(-1,636) (-21,812) kWh |
$(-37,624) (-2,148) MMBtu |
$64,250 2,933 MMBtu |
$4,576 933 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | LPG | Fuel Oil #4 | Water Disposal | Electricity Usage | LPG | Fuel Oil #4 | Water Disposal |