Select a Center

Arizona State University
Boise State University
Case Western Reserve University
Clemson University
Colorado State University
Georgia Institute of Technology
Indiana University-Purdue University
Lehigh University
Louisiana State University
North Carolina State
Oklahoma State University
Oregon State University
San Diego State University
San Francisco State University
Syracuse University
Tennessee Technological University
Texas A&M, College Station
University of Alabama
University of Dayton
University of Delaware
University of Florida
University of Illinois, Chicago
University of Kentucky
University of Massachusetts
University of Miami
University of Missouri-Columbia
University of Nebraska–Lincoln
University of Texas Rio Grande Valley
University of Utah
University of Wisconsin, Milwaukee
West Virginia University
IAC logo
IAC Assessment: MA0748
Sponsored by:
EERE AMO
IAC logo
IAC Assessment: MA0748
Due to University and State restrictions around the country, all IAC assessment activities are temporarily on hold.
Click here for details about Coronavirus (COVID-19) Recovery Support programs
IAC Center University of Massachusetts
Assessment Year 2015
Principal Product Insulated wire
NAICS 332618 - Other Fabricated Wire Product Manufacturing
SIC 3357 - Nonferrous Wiredrawing & Insulating
Sales $65,000,000
# of Employees 104
Plant Area (Sq.Ft.) 73,563
Annual Production 24,000 Thousand Feet
Production Hrs. Annual 6,864
Location (State) VT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $299,403 3,242,047 kWh $0.09
Electricity Demand $126,088 14,762 kW/month $8.54
Electricity Fees $1,411 - $ -
Natural Gas $69,655 8,512 MMBtu $8.18
TOTAL ENERGY COSTS $496,557
RECOMMENDED SAVINGS* $54,918 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,713
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.2511 INSULATE BARE EQUIPMENT Savings:
$35,959
Cost:
$11,580
$35,959 390,862 - - $35,959
390,862
kWh
-
-
MMBtu
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$9,716
Cost:
$9,850
- - $9,716 1,214 -
-
kWh
$9,716
1,214
MMBtu
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$4,530
Cost:
$9,000
- - $4,530 566 -
-
kWh
$4,530
566
MMBtu
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,687
Cost:
$5,365
$1,687 18,334 - - $1,687
18,334
kWh
-
-
MMBtu
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$1,137
Cost:
$100
$1,137 12,355 - - $1,137
12,355
kWh
-
-
MMBtu
06: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$1,168
Cost:
$500
- - $1,168 146 -
-
kWh
$1,168
146
MMBtu
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$721
Cost:
$2,245
$721 7,833 - - $721
7,833
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$54,918
Cost:
$38,640
$39,504 429,384 $15,414 1,926 $39,504
429,384
kWh
$15,414
1,926
MMBtu
TOTAL IMPLEMENTED Savings:
$4,713
Cost:
$8,210
$3,545 38,522 $1,168 146 $3,545
38,522
kWh
$1,168
146
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas