Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2016 |
Principal Product | Rubber Coated Fabrics and Clothing |
NAICS | 313320 - Fabric Coating Mills |
SIC | 3069 - Fabricated Rubber Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 14 |
Plant Area (Sq.Ft.) | 88,000 |
Annual Production | 4,500 Thousand Feet |
Production Hrs. Annual | 2,040 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $45,119 | 270,866 | kWh | $0.17 |
Electricity Demand | $15,997 | 2,717 | kW-months/year | $5.89 |
Electricity Fees | $462 | - | $ | - |
Natural Gas | $37,797 | 4,023 | MMBtu | $9.40 |
TOTAL ENERGY COSTS | $99,375 | |||
RECOMMENDED SAVINGS* | $7,924 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,086 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $3,870 Cost: $3,830 |
$3,870 | 23,171 | - | - | - | - | - | - |
$3,870 23,171 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $939 Cost: $3,914 |
- | - | - | - | $939 | 100 | - | - |
- - kWh |
- - kW-months/year |
$939 100 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $871 Cost: $1,000 |
$871 | 5,218 | - | - | - | - | - | - |
$871 5,218 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4151 MINIMIZE WATER USAGE |
Savings: $587 Cost: $3,650 |
$(-41) | (-248) | - | - | - | - | $628 | 9,261 |
$(-41) (-248) kWh |
- - kW-months/year |
- - MMBtu |
$628 9,261 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $515 Cost: $3,480 |
- | - | $515 | 89 | - | - | - | - |
- - kWh |
$515 89 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2153 CLOSE OFF UNNEEDED STEAM LINES |
Savings: $376 Cost: $4,348 |
- | - | - | - | $376 | 40 | - | - |
- - kWh |
- - kW-months/year |
$376 40 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $331 Cost: $2,648 |
$331 | 1,983 | - | - | - | - | - | - |
$331 1,983 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $313 Cost: $1,944 |
- | - | - | - | $313 | 33 | - | - |
- - kWh |
- - kW-months/year |
$313 33 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE |
Savings: $122 Cost: $300 |
$122 | 728 | - | - | - | - | - | - |
$122 728 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $7,924 Cost: $25,114 |
$5,153 | 30,852 | $515 | 89 | $1,628 | 173 | $628 | 9,261 | $5,153 30,852 kWh |
$515 89 kW-months/year |
$1,628 173 MMBtu |
$628 9,261 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,086 Cost: $14,856 |
$830 | 4,970 | - | - | $1,628 | 173 | $628 | 9,261 | $830 4,970 kWh |
- - kW-months/year |
$1,628 173 MMBtu |
$628 9,261 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Electricity Usage | Electricity Demand | Natural Gas | Water Usage |