IAC logo
IAC Assessment: MA0772
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MA0772
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2017
Principal Product Metal finishing
NAICS 332813 - Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3479 - Metal Coating And Allied Services
Sales $1,000,000-$5,000,000
# of Employees 54
Plant Area (Sq.Ft.) 120,000
Annual Production 600 Units
Production Hrs. Annual 2,210
Location (State) RI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $42,202 372,775 kWh $0.11
Electricity Demand $6,199 1,954 kW-months/year $3.17
Electricity Fees $14,076 - $ -
Natural Gas $59,309 6,700 MMBtu $8.85
TOTAL ENERGY COSTS $121,786
RECOMMENDED SAVINGS* $8,856 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,600
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$3,553
Cost:
$10,235
$3,553 31,441 - - $3,553
31,441
kWh
-
-
kW-months/year
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,550
Cost:
$7,200
$2,550 22,570 - - $2,550
22,570
kWh
-
-
kW-months/year
03: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,069
Cost:
$3,189
- - $1,069 337 -
-
kWh
$1,069
337
kW-months/year
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$602
Cost:
$20
$602 5,332 - - $602
5,332
kWh
-
-
kW-months/year
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$551
Cost:
$300
$551 4,875 - - $551
4,875
kWh
-
-
kW-months/year
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$499
Cost:
$20
$499 4,417 - - $499
4,417
kWh
-
-
kW-months/year
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$32
Cost:
$144
$32 283 - - $32
283
kWh
-
-
kW-months/year
TOTAL RECOMMENDED Savings:
$8,856
Cost:
$21,108
$7,787 68,918 $1,069 337 $7,787
68,918
kWh
$1,069
337
kW-months/year
TOTAL IMPLEMENTED Savings:
$3,600
Cost:
$7,520
$3,600 31,862 - - $3,600
31,862
kWh
-
-
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand