Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Massachusetts
Assessment Year 2021
Principal Product Precious Metals
NAICS 331410 - Nonferrous Metal (except Aluminum) Smelting and Refining
SIC 3339 - Primary Nonferrous Metals, Nec
Sales $10,000,000-$50,000,000
# of Employees 106
Plant Area (Sq.Ft.) 61,000
Annual Production 1,000,000 Pounds
Production Hrs. Annual 7,488
Location (State) MA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $619,375 5,967,000 kWh $0.10
Electricity Demand $264,628 18,492 kW-months/year $14.31
Electricity Fees $(-86,001) - $ -
Natural Gas $188,672 28,962 MMBtu $6.51
TOTAL ENERGY COSTS $1,014,163
RECOMMENDED SAVINGS* $67,815 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $24,594
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Usage Water Disposal Electricity Usage Electricity Demand Natural Gas Water Usage Water Disposal
$ kWh $ kW-months/year $ MMBtu $ Tgal $ Tgal
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$32,062
Cost:
$75,000
- - - - $18,246 2,801 $6,583 1,210 $7,233 1,210 -
-
kWh
-
-
kW-months/year
$18,246
2,801
MMBtu
$6,583
1,210
Tgal
$7,233
1,210
Tgal
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$18,909
Cost:
$26,950
$18,909 181,821 - - - - - - - - $18,909
181,821
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
Tgal
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$6,022
Cost:
$11,050
$6,022 57,907 - - - - - - - - $6,022
57,907
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
Tgal
04: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$5,685
Cost:
$2,000
- - - - - - - - $5,685 951 -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$5,685
951
Tgal
05: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING Savings:
$2,962
Cost:
$10,800
$1,116 10,731 $1,846 129 - - - - - - $1,116
10,731
kWh
$1,846
129
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
Tgal
06: 3.4151 MINIMIZE WATER USAGE Savings:
$1,374
Cost:
$3,230
- - - - - - $655 120 $719 120 -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$655
120
Tgal
$719
120
Tgal
07: 2.2511 INSULATE BARE EQUIPMENT Savings:
$801
Cost:
$1,550
- - - - $801 123 - - - - -
-
kWh
-
-
kW-months/year
$801
123
MMBtu
-
-
Tgal
-
-
Tgal
TOTAL RECOMMENDED Savings:
$67,815
Cost:
$130,580
$26,047 250,459 $1,846 129 $19,047 2,924 $7,238 1,329 $13,637 2,280 $26,047
250,459
kWh
$1,846
129
kW-months/year
$19,047
2,924
MMBtu
$7,238
1,329
Tgal
$13,637
2,280
Tgal
TOTAL IMPLEMENTED Savings:
$24,594
Cost:
$28,950
$18,909 181,821 - - - - - - $5,685 951 $18,909
181,821
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$5,685
951
Tgal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ Tgal
Electricity Usage Electricity Demand Natural Gas Water Usage Water Disposal Electricity Usage Electricity Demand Natural Gas Water Usage Water Disposal