Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Massachusetts |
---|---|
Assessment Year | 2022 |
Principal Product | Wastewater transfer |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | <$500,000 |
# of Employees | 3 |
Plant Area (Sq.Ft.) | 5,400 |
Annual Production | 50,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | MA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $50,449 | 335,360 | kWh | $0.15 |
Electricity Demand | $41,973 | 1,564 | kW-months/year | $26.84 |
Electricity Fees | $216 | - | $ | - |
Fuel Oil #2 | $30,268 | 2,384 | MMBtu | $12.70 |
TOTAL ENERGY COSTS | $122,906 | |||
RECOMMENDED SAVINGS* | $45,702 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,585 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Electricity Usage | Electricity Demand | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $29,117 Cost: $6,950 |
$19,837 | 132,247 | - | - | $9,280 | 731 |
$19,837 132,247 kWh |
- - kW-months/year |
$9,280 731 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $10,258 Cost: $840 |
- | - | - | - | $10,258 | 808 |
- - kWh |
- - kW-months/year |
$10,258 808 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING |
Savings: $5,709 Cost: $2,500 |
$4,582 | 30,551 | $1,127 | 42 | - | - |
$4,582 30,551 kWh |
$1,127 42 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING |
Savings: $618 Cost: $94,050 |
$(-23,800) | (-158,664) | $(-5,850) | (-218) | $30,268 | 2,384 |
$(-23,800) (-158,664) kWh |
$(-5,850) (-218) kW-months/year |
$30,268 2,384 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $45,702 Cost: $104,340 |
$619 | 4,134 | $(-4,723) | (-176) | $49,806 | 3,923 | $619 4,134 kWh |
$(-4,723) (-176) kW-months/year |
$49,806 3,923 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,585 Cost: $97,390 |
$(-19,218) | (-128,113) | $(-4,723) | (-176) | $40,526 | 3,192 | $(-19,218) (-128,113) kWh |
$(-4,723) (-176) kW-months/year |
$40,526 3,192 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Electricity Usage | Electricity Demand | Fuel Oil #2 |