IAC Assessment: ME0135
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ME0135
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Maine
Assessment Year 1994
Principal Product Shoes
NAICS n/a
SIC 3143 - Men's Footwear, Except Athletic
Sales $5,000,000-$10,000,000
# of Employees 300
Plant Area (Sq.Ft.) 60,000
Annual Production 0 Units
Production Hrs. Annual 2,000
Location (State) ME
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $128,786 1,106,975 kWh $0.12
Fuel Oil #6 $23,772 7,048 MMBtu $3.37
TOTAL ENERGY COSTS $152,558
RECOMMENDED SAVINGS* $14,005 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,107
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #6 Electricity Usage Fuel Oil #6
$ kWh $ MMBtu
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$390
Cost:
$450
$390 3,224 - - $390
3,224
kWh
-
-
MMBtu
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$817
Cost:
$350
- - $817 242 -
-
kWh
$817
242
MMBtu
03: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$5,700
Cost:
$4,000
$5,700 48,945 - - $5,700
48,945
kWh
-
-
MMBtu
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$760
Cost:
$600
$760 6,448 - - $760
6,448
kWh
-
-
MMBtu
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,600
Cost:
$5,300
$2,600 22,274 - - $2,600
22,274
kWh
-
-
MMBtu
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,146
Cost:
$500
$1,146 9,965 - - $1,146
9,965
kWh
-
-
MMBtu
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,900
Cost:
$600
$1,900 16,413 - - $1,900
16,413
kWh
-
-
MMBtu
08: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$692
Cost:
-
$692 5,862 - - $692
5,862
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$14,005
Cost:
$11,800
$13,188 113,131 $817 242 $13,188
113,131
kWh
$817
242
MMBtu
TOTAL IMPLEMENTED Savings:
$3,107
Cost:
$1,400
$2,290 19,637 $817 242 $2,290
19,637
kWh
$817
242
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Fuel Oil #6 Electricity Usage Fuel Oil #6