Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Maine |
---|---|
Assessment Year | 1998 |
Principal Product | slippers |
NAICS | n/a |
SIC | 3142 - House Slippers |
Sales | $10,000,000-$50,000,000 |
# of Employees | 85 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 850,000 Pieces |
Production Hrs. Annual | 3,003 |
Location (State) | ME |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $14,921 | 179,660 | kWh | $0.08 |
Electricity Demand | $4,093 | 761 | kW-months/year | $5.38 |
Electricity Fees | $1,554 | - | $ | - |
Fuel Oil #2 | $7,588 | 1,288 | MMBtu | $5.89 |
TOTAL ENERGY COSTS | $29,270 | |||
RECOMMENDED SAVINGS* | $8,141 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $4,662 Cost: $3,600 |
- | - | - | - | $4,662 | 810 | - | - | - | - |
- - kWh |
- - MMBtu |
$4,662 810 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $1,109 Cost: - |
- | - | - | - | - | - | - | - | $1,109 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
- - lb |
$1,109 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $432 Cost: - |
- | - | - | - | - | - | - | - | $432 | - |
- - kWh |
- - MMBtu |
- - MMBtu |
- - lb |
$432 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $407 Cost: $800 |
$407 | 4,982 | - | - | - | - | - | - | - | - |
$407 4,982 kWh |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) |
Savings: $211 Cost: $520 |
- | - | - | - | $211 | 56 | - | - | - | - |
- - kWh |
- - MMBtu |
$211 56 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $156 Cost: $200 |
- | - | $156 | 4 | - | - | - | - | - | - |
- - kWh |
$156 4 MMBtu |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $60 Cost: - |
- | - | - | - | $60 | - | - | - | - | - |
- - kWh |
- - MMBtu |
$60 - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $816 Cost: $2,640 |
- | - | - | - | - | - | $816 | 7,600 | - | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$816 7,600 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $288 Cost: - |
- | - | - | - | - | - | $288 | 1,400 | - | - |
- - kWh |
- - MMBtu |
- - MMBtu |
$288 1,400 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $8,141 Cost: $7,760 |
$407 | 4,982 | $156 | 4 | $4,933 | 866 | $1,104 | 9,000 | $1,541 | - | $407 4,982 kWh |
$156 4 MMBtu |
$4,933 866 MMBtu |
$1,104 9,000 lb |
$1,541 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #2 | Solid Waste (non-haz) | Administrative Changes |