Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2001 |
Principal Product | Ship and boat equipment |
NAICS | n/a |
SIC | 3429 - Hardware, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 490 |
Plant Area (Sq.Ft.) | 430,000 |
Annual Production | 45,000,000 Units |
Production Hrs. Annual | 4,188 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $643,050 | 10,126,771 | kWh | $0.06 |
TOTAL ENERGY COSTS | $704,461 | |||
RECOMMENDED SAVINGS* | $238,135 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $44,044 |
#|Description |
Savings Cost |
Status | Electricity Usage | Water Disposal | Administrative Changes | Primary Product | Electricity Usage | Water Disposal | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,015 Cost: $10,000 |
$4,015 | 66,816 | - | - | - | - | - | - |
$4,015 66,816 kWh |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4222 INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN |
Savings: $40,000 Cost: $15,120 |
- | - | - | - | $40,000 | - | - | - |
- - kWh |
- - Tgal |
$40,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,044 Cost: $312 |
$4,044 | 63,189 | - | - | - | - | - | - |
$4,044 63,189 kWh |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4155 METER WASTE WATER |
Savings: $25,076 Cost: $3,650 |
- | - | $25,076 | 6,255 | - | - | - | - |
- - kWh |
$25,076 6,255 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $125,000 Cost: $136,000 |
- | - | - | - | - | - | $125,000 | - |
- - kWh |
- - Tgal |
- - $ |
$125,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $40,000 Cost: $2,900 |
- | - | - | - | $40,000 | - | - | - |
- - kWh |
- - Tgal |
$40,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $238,135 Cost: $167,982 |
$8,059 | 130,005 | $25,076 | 6,255 | $80,000 | - | $125,000 | - | $8,059 130,005 kWh |
$25,076 6,255 Tgal |
$80,000 - $ |
$125,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $44,044 Cost: $3,212 |
$4,044 | 63,189 | - | - | $40,000 | - | - | - | $4,044 63,189 kWh |
- - Tgal |
$40,000 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Water Disposal | Administrative Changes | Primary Product | Electricity Usage | Water Disposal | Administrative Changes | Primary Product |