Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2001 |
Principal Product | Screen printing and embroidery |
NAICS | n/a |
SIC | 2396 - Automotive And Apparel Trimmings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 203 |
Plant Area (Sq.Ft.) | 70,000 |
Annual Production | 5,709,000 Pieces |
Production Hrs. Annual | 2,210 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $86,437 | 1,627,765 | kWh | $0.05 |
Electricity Demand | $42,565 | 4,846 | kW-months/year | $8.78 |
Natural Gas | $20,398 | 2,384 | MMBtu | $8.56 |
TOTAL ENERGY COSTS | $149,400 | |||
RECOMMENDED SAVINGS* | $177,285 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Administrative Changes | Primary Product | Electricity Usage | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $5,105 Cost: $2,513 |
$5,105 | 63,812 | - | - | - | - |
$5,105 63,812 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,467 Cost: $333 |
$2,467 | 30,832 | - | - | - | - |
$2,467 30,832 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $16,244 Cost: $2,084 |
$16,244 | 203,050 | - | - | - | - |
$16,244 203,050 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,608 Cost: $312 |
$4,608 | 57,600 | - | - | - | - |
$4,608 57,600 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $22,646 Cost: $7,000 |
- | - | - | - | $22,646 | - |
- - kWh |
- - $ |
$22,646 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $6,215 Cost: $1,126 |
- | - | $6,215 | - | - | - |
- - kWh |
$6,215 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $120,000 Cost: $44,200 |
- | - | - | - | $120,000 | - |
- - kWh |
- - $ |
$120,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $177,285 Cost: $57,568 |
$28,424 | 355,294 | $6,215 | - | $142,646 | - | $28,424 355,294 kWh |
$6,215 - $ |
$142,646 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Administrative Changes | Primary Product | Electricity Usage | Administrative Changes | Primary Product |