Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2001 |
Principal Product | Aircraft generator repair |
NAICS | n/a |
SIC | 3728 - Aircraft Parts And Equipment, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 38,400 |
Annual Production | 8,000 Pieces |
Production Hrs. Annual | 2,210 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $72,125 | 1,057,805 | kWh | $0.07 |
Electricity Demand | $19,902 | 2,451 | kW-months/year | $8.12 |
TOTAL ENERGY COSTS | $92,027 | |||
RECOMMENDED SAVINGS* | $619,918 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $609,256 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Primary Product | Electricity Usage | Electricity Demand | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $59,040 Cost: $5,100 |
- | - | - | - | $59,040 | - |
- - kWh |
- - kW-months/year |
$59,040 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $73,364 Cost: $5,100 |
- | - | - | - | $73,364 | - |
- - kWh |
- - kW-months/year |
$73,364 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $18,892 Cost: $5,100 |
- | - | - | - | $18,892 | - |
- - kWh |
- - kW-months/year |
$18,892 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.322 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL |
Savings: $114,007 Cost: $5,100 |
- | - | - | - | $114,007 | - |
- - kWh |
- - kW-months/year |
$114,007 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS |
Savings: $316,160 Cost: $164,000 |
- | - | - | - | $316,160 | - |
- - kWh |
- - kW-months/year |
$316,160 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $27,793 Cost: $19 |
$7,418 | 109,093 | $20,375 | 2,509 | - | - |
$7,418 109,093 kWh |
$20,375 2,509 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $10,662 Cost: $760 |
$10,662 | 95,118 | - | - | - | - |
$10,662 95,118 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $619,918 Cost: $185,179 |
$18,080 | 204,211 | $20,375 | 2,509 | $581,463 | - | $18,080 204,211 kWh |
$20,375 2,509 kW-months/year |
$581,463 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $609,256 Cost: $184,419 |
$7,418 | 109,093 | $20,375 | 2,509 | $581,463 | - | $7,418 109,093 kWh |
$20,375 2,509 kW-months/year |
$581,463 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Primary Product | Electricity Usage | Electricity Demand | Primary Product |