Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2002 |
Principal Product | Aluminum windows, doors, hurricane shutters |
NAICS | n/a |
SIC | 3354 - Aluminum Extruded Products |
Sales | $5,000,000-$10,000,000 |
# of Employees | 19 |
Plant Area (Sq.Ft.) | 67,500 |
Annual Production | 15,000,000 Pieces |
Production Hrs. Annual | 2,125 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $8,918 | 129,882 | kWh | $0.07 |
Electricity Demand | $4,628 | 570 | kW-months/year | $8.12 |
TOTAL ENERGY COSTS | $13,546 | |||
RECOMMENDED SAVINGS* | $71,857 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,532 |
#|Description |
Savings Cost |
Status | Electricity Usage | Primary Product | Electricity Usage | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.112 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL |
Savings: $26,325 Cost: $45,000 |
- | - | $26,325 | - |
- - kWh |
$26,325 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.512 CONDENSE OPERATION INTO ONE BUILDING |
Savings: $23,625 Cost: $714 |
- | - | $23,625 | - |
- - kWh |
$23,625 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.323 OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS |
Savings: $16,250 Cost: $60 |
- | - | $16,250 | - |
- - kWh |
$16,250 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,497 Cost: $60 |
$5,497 | 91,620 | - | - |
$5,497 91,620 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $160 Cost: $2 |
$160 | 2,669 | - | - |
$160 2,669 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $71,857 Cost: $45,836 |
$5,657 | 94,289 | $66,200 | - | $5,657 94,289 kWh |
$66,200 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,532 Cost: $836 |
$5,657 | 94,289 | $39,875 | - | $5,657 94,289 kWh |
$39,875 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||