Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2004 |
Principal Product | Aircraft engine and engine parts manufacture |
NAICS | 336412 - Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724 - Aircraft Engines And Engine Parts |
Sales | $1,000,000-$5,000,000 |
# of Employees | 45 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 19,200 Pieces |
Production Hrs. Annual | 2,125 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $162,958 | 3,342,800 | kWh | $0.05 |
Electricity Demand | $78,258 | 9,578 | kW-months/year | $8.17 |
Electricity Fees | $27,718 | - | $ | - |
Natural Gas | $149,521 | 21,286 | MMBtu | $7.02 |
TOTAL ENERGY COSTS | $418,455 | |||
RECOMMENDED SAVINGS* | $206,468 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,558 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Primary Product | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $3,778 Cost: $600 |
- | - | - | - | - | - | $3,778 | - | - | - |
- - kWh |
- - MMBtu |
- - $ |
$3,778 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $70,081 Cost: $2,300 |
$70,081 | 1,250,823 | - | - | - | - | - | - | - | - |
$70,081 1,250,823 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $120,575 Cost: - |
$18,825 | 233,996 | $10,460 | 1,490 | $(-75,000) | - | - | - | $166,290 | - |
$18,825 233,996 kWh |
$10,460 1,490 MMBtu |
$(-75,000) - $ |
- - $ |
$166,290 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $2,100 Cost: $5,660 |
$2,100 | 42,321 | - | - | - | - | - | - | - | - |
$2,100 42,321 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $862 Cost: $543 |
- | - | $862 | 153 | - | - | - | - | - | - |
- - kWh |
$862 153 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,100 Cost: $144 |
$2,100 | 42,320 | - | - | - | - | - | - | - | - |
$2,100 42,320 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,514 Cost: $894 |
$7,090 | 142,874 | - | - | $(-576) | - | - | - | - | - |
$7,090 142,874 kWh |
- - MMBtu |
$(-576) - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $458 Cost: $186 |
$458 | 15,733 | - | - | - | - | - | - | - | - |
$458 15,733 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $206,468 Cost: $10,327 |
$100,654 | 1,728,067 | $11,322 | 1,643 | $(-75,576) | - | $3,778 | - | $166,290 | - | $100,654 1,728,067 kWh |
$11,322 1,643 MMBtu |
$(-75,576) - $ |
$3,778 - $ |
$166,290 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,558 Cost: $330 |
$2,558 | 58,053 | - | - | - | - | - | - | - | - | $2,558 58,053 kWh |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Primary Product | Electricity Usage | Natural Gas | Personnel Changes | Administrative Changes | Primary Product |