IAC logo
IAC Assessment: MI0117
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MI0117
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Miami
Assessment Year 2005
Principal Product industrial hydraulic valves
NAICS 332999 - All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499 - Fabricated Metal Products, Nec
Sales $50,000,000-$100,000,000
# of Employees 380
Plant Area (Sq.Ft.) 50,000
Annual Production 650,000 Pieces
Production Hrs. Annual 5,250
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $306,863 6,006,400 kWh $0.05
Electricity Demand $113,467 13,741 kW-months/year $8.26
Electricity Fees $27,888 - $ -
TOTAL ENERGY COSTS $448,218
RECOMMENDED SAVINGS* $29,038 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $25,373
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Administrative Changes Electricity Usage Electricity Demand Personnel Changes Administrative Changes
$ kWh $ kW-months/year $ $ $ $
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$16,898
Cost:
$1,350
$16,898 330,750 - - - - - - $16,898
330,750
kWh
-
-
kW-months/year
-
-
$
-
-
$
02: 2.2523 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS Savings:
$4,463
Cost:
$11,400
$(-95) (-1,865) - - - - $4,558 - $(-95)
(-1,865)
kWh
-
-
kW-months/year
-
-
$
$4,558
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,012
Cost:
$906
$2,679 52,441 $1,557 188 $(-224) - - - $2,679
52,441
kWh
$1,557
188
kW-months/year
$(-224)
-
$
-
-
$
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$2,621
Cost:
$56
$1,968 38,518 $653 79 - - - - $1,968
38,518
kWh
$653
79
kW-months/year
-
-
$
-
-
$
05: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT Savings:
$1,044
Cost:
$5,024
$843 16,493 $201 24 - - - - $843
16,493
kWh
$201
24
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$29,038
Cost:
$18,736
$22,293 436,337 $2,411 291 $(-224) - $4,558 - $22,293
436,337
kWh
$2,411
291
kW-months/year
$(-224)
-
$
$4,558
-
$
TOTAL IMPLEMENTED Savings:
$25,373
Cost:
$13,656
$19,482 381,326 $1,557 188 $(-224) - $4,558 - $19,482
381,326
kWh
$1,557
188
kW-months/year
$(-224)
-
$
$4,558
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Administrative Changes Electricity Usage Electricity Demand Personnel Changes Administrative Changes