Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2015 |
Principal Product | Manifolds |
NAICS | 332912 - Fluid Power Valve and Hose Fitting Manufacturing |
SIC | 3492 - Fluid Power Valves & Hose Fittings |
Sales | $50,000,000-$100,000,000 |
# of Employees | 267 |
Plant Area (Sq.Ft.) | 83,000 |
Annual Production | 52,000 Pieces |
Production Hrs. Annual | 8,008 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $248,501 | 5,457,335 | kWh | $0.05 |
Electricity Demand | $101,845 | 8,173 | kW-months/year | $12.46 |
Electricity Fees | $21,261 | - | $ | - |
TOTAL ENERGY COSTS | $371,607 | |||
RECOMMENDED SAVINGS* | $116,420 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $51,932 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2514 COVER OPEN TANKS |
Savings: $36,126 Cost: $25,100 |
$36,126 | 785,343 | - | - |
$36,126 785,343 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7425 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD |
Savings: $22,640 Cost: $52,920 |
$22,640 | 492,174 | - | - |
$22,640 492,174 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $15,400 Cost: $80 |
$15,400 | 334,680 | - | - |
$15,400 334,680 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7292 LOWER CEILING TO REDUCE CONDITIONED SPACE |
Savings: $13,892 Cost: $76,650 |
$13,892 | 301,998 | - | - |
$13,892 301,998 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4323 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT |
Savings: $8,325 Cost: $4,691 |
$5,185 | 112,725 | $3,140 | 252 |
$5,185 112,725 kWh |
$3,140 252 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,096 Cost: $1,660 |
$7,485 | 162,710 | $611 | 49 |
$7,485 162,710 kWh |
$611 49 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $6,621 Cost: $5,370 |
$2,737 | 57,015 | $3,884 | 313 |
$2,737 57,015 kWh |
$3,884 313 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $3,310 Cost: $6,660 |
$2,338 | 51,920 | $972 | 78 |
$2,338 51,920 kWh |
$972 78 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,010 Cost: $40 |
$1,262 | 27,425 | $748 | 60 |
$1,262 27,425 kWh |
$748 60 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $116,420 Cost: $173,171 |
$107,065 | 2,325,990 | $9,355 | 752 | $107,065 2,325,990 kWh |
$9,355 752 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $51,932 Cost: $129,650 |
$51,932 | 1,128,852 | - | - | $51,932 1,128,852 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |