Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Miami |
---|---|
Assessment Year | 2023 |
Principal Product | Ready-mixed Concrete |
NAICS | 327320 - Ready-Mix Concrete Manufacturing |
SIC | 3273 - Ready-mixed Concrete |
Sales | $100,000,000-$500,000,000 |
# of Employees | 35 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 690,000 Tons |
Production Hrs. Annual | 3,640 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $34,381 | 531,360 | kWh | $0.06 |
Electricity Demand | $28,464 | 2,397 | kW-months/year | $11.87 |
Electricity Fees | $16,466 | - | $ | - |
Fuel Oil #2 | $800,000 | 29,543 | MMBtu | $27.08 |
TOTAL ENERGY COSTS | $879,311 | |||
RECOMMENDED SAVINGS* | $32,515 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,350 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Ancillary Material Cost | Electricity Usage | Electricity Demand | Fuel Oil #2 | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8226 INCREASE EFFICIENCY OF TRUCKS |
Savings: $15,746 Cost: $16,000 |
- | - | - | - | $11,996 | 443 | $3,750 | - |
- - kWh |
- - kW-months/year |
$11,996 443 MMBtu |
$3,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $6,321 Cost: $5,505 |
$3,946 | 60,700 | $2,375 | 200 | - | - | - | - |
$3,946 60,700 kWh |
$2,375 200 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $4,121 Cost: - |
$4,121 | 63,396 | - | - | - | - | - | - |
$4,121 63,396 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,229 Cost: $1,980 |
$2,398 | 36,895 | $831 | 70 | - | - | - | - |
$2,398 36,895 kWh |
$831 70 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4325 UPGRADE CONVEYORS |
Savings: $2,168 Cost: $4,160 |
$1,353 | 20,808 | $815 | 69 | - | - | - | - |
$1,353 20,808 kWh |
$815 69 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $930 Cost: $280 |
$586 | 9,017 | $344 | 29 | - | - | - | - |
$586 9,017 kWh |
$344 29 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $32,515 Cost: $27,925 |
$12,404 | 190,816 | $4,365 | 368 | $11,996 | 443 | $3,750 | - | $12,404 190,816 kWh |
$4,365 368 kW-months/year |
$11,996 443 MMBtu |
$3,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,350 Cost: $1,980 |
$6,519 | 100,291 | $831 | 70 | - | - | - | - | $6,519 100,291 kWh |
$831 70 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Ancillary Material Cost | Electricity Usage | Electricity Demand | Fuel Oil #2 | Ancillary Material Cost |