Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1995 |
Principal Product | Gloves |
NAICS | n/a |
SIC | 2381 - Fabric Dress And Work Gloves |
Sales | $10,000,000-$50,000,000 |
# of Employees | 180 |
Plant Area (Sq.Ft.) | 50,680 |
Annual Production | 19,200,000 Pieces |
Production Hrs. Annual | 1,728 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $61,894 | 731,829 | kWh | $0.08 |
Natural Gas | $4,072 | 966 | MMBtu | $4.22 |
TOTAL ENERGY COSTS | $65,966 | |||
RECOMMENDED SAVINGS* | $5,108 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,502 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $156 Cost: $142 |
$156 | 2,052 | - | - |
$156 2,052 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,060 Cost: $1,510 |
- | - | $1,060 | 252 |
- - kWh |
$1,060 252 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $175 Cost: $380 |
$175 | 5,569 | - | - |
$175 5,569 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2625 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE |
Savings: $3,275 Cost: $800 |
$2,475 | 20,516 | $800 | 180 |
$2,475 20,516 kWh |
$800 180 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $442 Cost: $75 |
$442 | 5,569 | - | - |
$442 5,569 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $5,108 Cost: $2,907 |
$3,248 | 33,706 | $1,860 | 432 | $3,248 33,706 kWh |
$1,860 432 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,502 Cost: $1,585 |
$442 | 5,569 | $1,060 | 252 | $442 5,569 kWh |
$1,060 252 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |