Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1996 |
Principal Product | processed catfish |
NAICS | n/a |
SIC | 2092 - Fresh Or Frozen Prepared Fish |
Sales | $50,000,000-$100,000,000 |
# of Employees | 223 |
Plant Area (Sq.Ft.) | 52,000 |
Annual Production | 35,000,000 Pounds |
Production Hrs. Annual | 2,080 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $332,354 | 5,577,374 | kWh | $0.06 |
Electricity Demand | $108,426 | 13,142 | kW-months/year | $8.25 |
Electricity Fees | $(-31,584) | - | $ | - |
Natural Gas | $25,368 | 5,983 | MMBtu | $4.24 |
TOTAL ENERGY COSTS | $444,069 | |||
RECOMMENDED SAVINGS* | $23,483 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | Water Disposal | Electricity Usage | Electricity Fees | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $10,735 Cost: $3,825 |
- | - | - | - | $10,735 | 2,532 | - | - |
- - kWh |
- - $ |
$10,735 2,532 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $8,132 Cost: $13,840 |
$9,311 | 175,557 | $(-1,179) | - | - | - | - | - |
$9,311 175,557 kWh |
$(-1,179) - $ |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,432 Cost: $930 |
$1,640 | 77,374 | $(-208) | - | - | - | - | - |
$1,640 77,374 kWh |
$(-208) - $ |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4155 METER WASTE WATER |
Savings: $3,184 Cost: $685 |
- | - | - | - | - | - | $3,184 | - |
- - kWh |
- - $ |
- - MMBtu |
$3,184 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,483 Cost: $19,280 |
$10,951 | 252,931 | $(-1,387) | - | $10,735 | 2,532 | $3,184 | - | $10,951 252,931 kWh |
$(-1,387) - $ |
$10,735 2,532 MMBtu |
$3,184 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - $ |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | Water Disposal | Electricity Usage | Electricity Fees | Natural Gas | Water Disposal |