Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 1997 |
Principal Product | switches, wiring harnesses, and heat resistor blocks |
NAICS | n/a |
SIC | 3643 - Current-carrying Wiring Devices |
Sales | $10,000,000-$50,000,000 |
# of Employees | 64 |
Plant Area (Sq.Ft.) | 45,000 |
Annual Production | 9,440,000 Pieces |
Production Hrs. Annual | 2,000 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $19,363 | 283,411 | kWh | $0.07 |
Electricity Fees | $6,662 | - | $ | - |
Natural Gas | $12,086 | 2,232 | MMBtu | $5.41 |
TOTAL ENERGY COSTS | $40,398 | |||
RECOMMENDED SAVINGS* | $14,848 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,456 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $95 Cost: $33 |
$81 | 1,758 | $14 | - | - | - | - | - | - | - |
$81 1,758 kWh |
$14 - $ |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $996 Cost: $522 |
- | - | - | - | $996 | 184 | - | - | - | - |
- - kWh |
- - $ |
$996 184 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7122 DISCONNECT BALLASTS |
Savings: $133 Cost: $44 |
$115 | 2,345 | $18 | - | - | - | - | - | - | - |
$115 2,345 kWh |
$18 - $ |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $5,880 Cost: $588 |
- | - | - | - | $5,880 | 1,085 | - | - | - | - |
- - kWh |
- - $ |
$5,880 1,085 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $5,352 Cost: $1,785 |
$4,608 | 96,717 | $744 | - | - | - | - | - | - | - |
$4,608 96,717 kWh |
$744 - $ |
- - MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $2,392 Cost: - |
- | - | - | - | - | - | $592 | 19,200 | $1,800 | - |
- - kWh |
- - $ |
- - MMBtu |
$592 19,200 lb |
$1,800 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $14,848 Cost: $2,972 |
$4,804 | 100,820 | $776 | - | $6,876 | 1,269 | $592 | 19,200 | $1,800 | - | $4,804 100,820 kWh |
$776 - $ |
$6,876 1,269 MMBtu |
$592 19,200 lb |
$1,800 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,456 Cost: $2,972 |
$4,804 | 100,820 | $776 | - | $6,876 | 1,269 | - | - | - | - | $4,804 100,820 kWh |
$776 - $ |
$6,876 1,269 MMBtu |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost | Electricity Usage | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Ancillary Material Cost |