Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2000 |
Principal Product | Catfish Products |
NAICS | n/a |
SIC | 2092 - Fresh Or Frozen Prepared Fish |
Sales | $10,000,000-$50,000,000 |
# of Employees | 215 |
Plant Area (Sq.Ft.) | 45,510 |
Annual Production | 18,200,000 Pounds |
Production Hrs. Annual | 2,080 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $306,004 | 6,255,569 | kWh | $0.05 |
Electricity Demand | $68,432 | 17,253 | kW-months/year | $3.97 |
Electricity Fees | $(-20,082) | - | $ | - |
Natural Gas | $17,106 | 3,213 | MMBtu | $5.32 |
TOTAL ENERGY COSTS | $371,460 | |||
RECOMMENDED SAVINGS* | $10,316 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,604 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes | Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $575 Cost: $371 |
- | - | - | - | $575 | 102 | - | - |
- - kWh |
- - $ |
$575 102 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $453 Cost: $472 |
$494 | 11,137 | $(-41) | - | - | - | - | - |
$494 11,137 kWh |
$(-41) - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $429 Cost: $158 |
$468 | 10,551 | $(-39) | - | - | - | - | - |
$468 10,551 kWh |
$(-39) - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2447 HEAT WATER WITH EXHAUST HEAT |
Savings: $4,758 Cost: $13,860 |
- | - | - | - | $4,758 | 847 | - | - |
- - kWh |
- - $ |
$4,758 847 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $3,175 Cost: $2,450 |
$3,461 | 76,788 | $(-286) | - | - | - | - | - |
$3,461 76,788 kWh |
$(-286) - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.812 APPLY FOR INVESTMENT INCENTIVES |
Savings: $926 Cost: $25 |
- | - | - | - | - | - | $926 | - |
- - kWh |
- - $ |
- - MMBtu |
$926 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,316 Cost: $17,336 |
$4,423 | 98,476 | $(-366) | - | $5,333 | 949 | $926 | - | $4,423 98,476 kWh |
$(-366) - $ |
$5,333 949 MMBtu |
$926 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,604 Cost: $2,608 |
$3,929 | 87,339 | $(-325) | - | - | - | - | - | $3,929 87,339 kWh |
$(-325) - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes | Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes |