Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2001 |
Principal Product | Optical network cable |
NAICS | n/a |
SIC | 3229 - Pressed And Blown Glass, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 23 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 400,000 Pieces |
Production Hrs. Annual | 2,000 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $40,988 | 697,200 | kWh | $0.06 |
Electricity Demand | $53 | 2,256 | kW-months/year | $0.02 |
Electricity Fees | $6,499 | - | $ | - |
Natural Gas | $7,585 | 1,301 | MMBtu | $5.83 |
TOTAL ENERGY COSTS | $62,143 | |||
RECOMMENDED SAVINGS* | $11,871 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,583 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Electricity Usage | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $2,288 Cost: $473 |
$1,856 | 35,595 | $432 | - |
$1,856 35,595 kWh |
$432 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $8,020 Cost: $100 |
$6,505 | 124,781 | $1,515 | - |
$6,505 124,781 kWh |
$1,515 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $234 Cost: $128 |
$106 | 2,035 | $128 | - |
$106 2,035 kWh |
$128 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,329 Cost: $729 |
$1,078 | 20,683 | $251 | - |
$1,078 20,683 kWh |
$251 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,871 Cost: $1,430 |
$9,545 | 183,094 | $2,326 | - | $9,545 183,094 kWh |
$2,326 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,583 Cost: $957 |
$7,689 | 147,499 | $1,894 | - | $7,689 147,499 kWh |
$1,894 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Electricity Usage | Electricity Fees |