Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2002 |
Principal Product | Upholstered furniture |
NAICS | n/a |
SIC | 2521 - Wood Office Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 162 |
Plant Area (Sq.Ft.) | 189,671 |
Annual Production | 182,500 Pieces |
Production Hrs. Annual | 2,025 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $36,335 | 908,000 | kWh | $0.04 |
Electricity Demand | $62,996 | 6,764 | kW-months/year | $9.31 |
Electricity Fees | $5,493 | - | $ | - |
Natural Gas | $24,860 | 3,685 | MMBtu | $6.75 |
TOTAL ENERGY COSTS | $147,975 | |||
RECOMMENDED SAVINGS* | $54,407 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,633 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,096 Cost: $1,739 |
- | - | - | - | - | - | $2,096 | 311 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,096 311 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,516 Cost: $577 |
$1,494 | 45,061 | - | - | $22 | - | - | - | - | - | - | - | - | - |
$1,494 45,061 kWh |
- - kW-months/year |
$22 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $864 Cost: $2,540 |
- | - | - | - | - | - | $864 | 128 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$864 128 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $675 Cost: $472 |
$665 | 20,063 | - | - | $10 | - | - | - | - | - | - | - | - | - |
$665 20,063 kWh |
- - kW-months/year |
$10 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7122 DISCONNECT BALLASTS |
Savings: $442 Cost: $255 |
$154 | 4,650 | $281 | 28 | $7 | - | - | - | - | - | - | - | - | - |
$154 4,650 kWh |
$281 28 kW-months/year |
$7 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.132 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST |
Savings: $48,814 Cost: $175,000 |
- | - | - | - | - | - | - | - | $9,471 | 118,387 | $5,490 | - | $33,853 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$9,471 118,387 lb |
$5,490 - $ |
$33,853 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $54,407 Cost: $180,583 |
$2,313 | 69,774 | $281 | 28 | $39 | - | $2,960 | 439 | $9,471 | 118,387 | $5,490 | - | $33,853 | - | $2,313 69,774 kWh |
$281 28 kW-months/year |
$39 - $ |
$2,960 439 MMBtu |
$9,471 118,387 lb |
$5,490 - $ |
$33,853 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,633 Cost: $1,304 |
$2,313 | 69,774 | $281 | 28 | $39 | - | - | - | - | - | - | - | - | - | $2,313 69,774 kWh |
$281 28 kW-months/year |
$39 - $ |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |