Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2002 |
Principal Product | Marin gears |
NAICS | n/a |
SIC | 3566 - Speed Changers, Drives, And Gears |
Sales | $1,000,000-$5,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 45,000 |
Annual Production | 2,550 Pieces |
Production Hrs. Annual | 2,040 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $32,686 | 434,640 | kWh | $0.08 |
Electricity Demand | $117 | 3,060 | kW-months/year | $0.04 |
Electricity Fees | $7,847 | - | $ | - |
Natural Gas | $8,426 | 1,155 | MMBtu | $7.30 |
TOTAL ENERGY COSTS | $50,369 | |||
RECOMMENDED SAVINGS* | $5,213 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,523 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $2,023 Cost: $50 |
- | - | - | - | $433 | - | $1,590 | - |
- - kWh |
- - $ |
$433 - MMBtu |
$1,590 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,672 Cost: $1,484 |
$1,421 | 27,259 | $251 | - | - | - | - | - |
$1,421 27,259 kWh |
$251 - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,018 Cost: $151 |
$865 | 16,588 | $153 | - | - | - | - | - |
$865 16,588 kWh |
$153 - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $500 Cost: $708 |
$425 | 8,154 | $75 | - | - | - | - | - |
$425 8,154 kWh |
$75 - $ |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $5,213 Cost: $2,393 |
$2,711 | 52,001 | $479 | - | $433 | - | $1,590 | - | $2,711 52,001 kWh |
$479 - $ |
$433 - MMBtu |
$1,590 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,523 Cost: $758 |
$425 | 8,154 | $75 | - | $433 | - | $1,590 | - | $425 8,154 kWh |
$75 - $ |
$433 - MMBtu |
$1,590 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Fees | Natural Gas | One-time Revenue or Avoided Cost |