Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2003 |
Principal Product | Pet Food Bags |
NAICS | n/a |
SIC | 2679 - Converted Paper Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 260 |
Plant Area (Sq.Ft.) | 244,000 |
Annual Production | 150,000,000 Pieces |
Production Hrs. Annual | 8,736 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $318,404 | 9,264,000 | kWh | $0.03 |
Electricity Demand | $177,396 | 16,703 | kW-months/year | $10.62 |
Electricity Fees | $7,006 | - | $ | - |
Natural Gas | $195,411 | 44,744 | MMBtu | $4.37 |
TOTAL ENERGY COSTS | $719,545 | |||
RECOMMENDED SAVINGS* | $152,660 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $118,492 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $118,492 Cost: $100 |
$80,086 | 2,330,123 | $36,729 | 3,530 | $1,677 | - | - | - |
$80,086 2,330,123 kWh |
$36,729 3,530 kW-months/year |
$1,677 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $12,922 Cost: $2,070 |
$8,789 | 255,724 | $3,952 | 351 | $181 | - | - | - |
$8,789 255,724 kWh |
$3,952 351 kW-months/year |
$181 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $2,495 Cost: $600 |
$515 | 14,976 | $1,946 | 173 | $34 | - | - | - |
$515 14,976 kWh |
$1,946 173 kW-months/year |
$34 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,427 Cost: $501 |
$3,380 | 98,340 | - | - | $47 | - | - | - |
$3,380 98,340 kWh |
- - kW-months/year |
$47 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7122 DISCONNECT BALLASTS |
Savings: $1,708 Cost: $1,602 |
$1,126 | 32,761 | $558 | 50 | $24 | - | - | - |
$1,126 32,761 kWh |
$558 50 kW-months/year |
$24 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,395 Cost: $1,350 |
$1,375 | 40,014 | - | - | $20 | - | - | - |
$1,375 40,014 kWh |
- - kW-months/year |
$20 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $462 Cost: $708 |
$455 | 13,253 | - | - | $7 | - | - | - |
$455 13,253 kWh |
- - kW-months/year |
$7 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.7198 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT |
Savings: $11,759 Cost: $3,266 |
- | - | - | - | - | - | $11,759 | 7,500 |
- - kWh |
- - kW-months/year |
- - $ |
$11,759 7,500 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $152,660 Cost: $10,197 |
$95,726 | 2,785,191 | $43,185 | 4,104 | $1,990 | - | $11,759 | 7,500 | $95,726 2,785,191 kWh |
$43,185 4,104 kW-months/year |
$1,990 - $ |
$11,759 7,500 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $118,492 Cost: $100 |
$80,086 | 2,330,123 | $36,729 | 3,530 | $1,677 | - | - | - | $80,086 2,330,123 kWh |
$36,729 3,530 kW-months/year |
$1,677 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) |