Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2011 |
Principal Product | Rubber Tires |
NAICS | 326211 - Tire Manufacturing (except Retreading) |
SIC | 3011 - Tires And Inner Tubes |
Sales | >$500,000,000 |
# of Employees | 1,750 |
Plant Area (Sq.Ft.) | 1,700,000 |
Annual Production | 14,000,000 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $3,563,617 | 126,518,370 | kWh | $0.03 |
Electricity Demand | $2,057,874 | 203,013 | kW-months/year | $10.14 |
Natural Gas | $4,776,784 | 589,976 | MMBtu | $8.10 |
TOTAL ENERGY COSTS | $10,398,275 | |||
RECOMMENDED SAVINGS* | $37,730 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS |
Savings: $23,582 Cost: $178,700 |
$15,528 | 554,560 | $7,706 | 760 | $348 | - |
$15,528 554,560 kWh |
$7,706 760 kW-months/year |
$348 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS |
Savings: $14,148 Cost: $132,820 |
$9,317 | 332,736 | $4,622 | 455 | $209 | - |
$9,317 332,736 kWh |
$4,622 455 kW-months/year |
$209 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $37,730 Cost: $311,520 |
$24,845 | 887,296 | $12,328 | 1,215 | $557 | - | $24,845 887,296 kWh |
$12,328 1,215 kW-months/year |
$557 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees |