Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2011 |
Principal Product | composite jet engine parts |
NAICS | 336412 - Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724 - Aircraft Engines And Engine Parts |
Sales | $100,000,000-$500,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 330,000 |
Annual Production | 1 Units |
Production Hrs. Annual | 8,760 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $598,849 | 11,858,400 | kWh | $0.05 |
Electricity Demand | $368,322 | 24,154 | kW-months/year | $15.25 |
Electricity Fees | $11,310 | - | $ | - |
TOTAL ENERGY COSTS | $978,481 | |||
RECOMMENDED SAVINGS* | $16,822 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $6,041 Cost: $1,900 |
$4,214 | 83,444 | $1,738 | 114 | $89 | - |
$4,214 83,444 kWh |
$1,738 114 kW-months/year |
$89 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7228 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM |
Savings: $3,680 Cost: $611 |
$3,626 | 71,818 | - | - | $54 | - |
$3,626 71,818 kWh |
- - kW-months/year |
$54 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $7,101 Cost: $13,781 |
$6,996 | 138,527 | - | - | $105 | - |
$6,996 138,527 kWh |
- - kW-months/year |
$105 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $16,822 Cost: $16,292 |
$14,836 | 293,789 | $1,738 | 114 | $248 | - | $14,836 293,789 kWh |
$1,738 114 kW-months/year |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees |