IAC Assessment: MS0423
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MS0423
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Mississippi State
Assessment Year 2023
Principal Product Credit/Debit card accounts, loans
NAICS 522130 - Credit Unions
SIC 6061 - Federal Credit Unions
Sales <$500,000
# of Employees 121
Plant Area (Sq.Ft.) 10,000
Annual Production 1 Units
Production Hrs. Annual 2,025
Location (State) MS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $65,296 487,349 kWh $0.13
Natural Gas $5,845 280 MMBtu $20.86
TOTAL ENERGY COSTS $71,141
RECOMMENDED SAVINGS* $18,388 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$1,305
Cost:
$8,100
$1,305 8,153 $1,305
8,153
kWh
02: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$15,239
Cost:
$68,005
$15,239 95,246 $15,239
95,246
kWh
03: 2.7423 REDUCE HEAT GAIN BY WINDOW TINTING Savings:
$1,844
Cost:
$4,100
$1,844 12,292 $1,844
12,292
kWh
TOTAL RECOMMENDED Savings:
$18,388
Cost:
$80,205
$18,388 115,691 $18,388
115,691
kWh
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - -
-
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage