Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Mississippi State |
---|---|
Assessment Year | 2024 |
Principal Product | Hydraulic/Fuel Tanks |
NAICS | 332313 - Plate Work Manufacturing |
SIC | 3599 - Industrial Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 124 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 18,341 Units |
Production Hrs. Annual | 3,325 |
Location (State) | MS |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $222,784 | 2,065,600 | kWh | $0.11 |
Electricity Demand | $32,108 | 8,208 | kW-months/year | $3.91 |
Electricity Fees | $(-6,737) | - | $ | - |
LPG | $18,620 | 915 | MMBtu | $20.35 |
TOTAL ENERGY COSTS | $266,775 | |||
RECOMMENDED SAVINGS* | $153,844 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | LPG | Electricity Usage | Electricity Fees | LPG | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS |
Savings: $37,679 Cost: $1,527 |
$37,679 | 342,535 | - | - | - | - |
$37,679 342,535 kWh |
- - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $101,423 Cost: $659,750 |
$101,423 | 922,025 | - | - | - | - |
$101,423 922,025 kWh |
- - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $10,911 Cost: $100,000 |
$(-7,709) | (-70,080) | - | - | $18,620 | 915 |
$(-7,709) (-70,080) kWh |
- - $ |
$18,620 915 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $3,222 Cost: - |
- | - | $3,222 | - | - | - |
- - kWh |
$3,222 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $609 Cost: $2,713 |
- | - | $609 | - | - | - |
- - kWh |
$609 - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $153,844 Cost: $763,990 |
$131,393 | 1,194,480 | $3,831 | - | $18,620 | 915 | $131,393 1,194,480 kWh |
$3,831 - $ |
$18,620 915 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - $ |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | LPG | Electricity Usage | Electricity Fees | LPG |