IAC Assessment: MS0437
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MS0437
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Mississippi State
Assessment Year 2024
Principal Product Power Take-Offs
NAICS 333995 - Fluid Power Cylinder and Actuator Manufacturing
SIC 3593 - Fluid Power Cylinders & Actuators
Sales $100,000,000-$500,000,000
# of Employees 171
Plant Area (Sq.Ft.) 80,000
Annual Production 203,200 Units
Production Hrs. Annual 4,600
Location (State) MS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $95,111 1,819,350 kWh $0.05
Electricity Demand $68,708 5,320 kW-months/year $12.91
Electricity Fees $46,952 - $ -
Fuel Oil #1 $473,760 19,787 MMBtu $23.94
TOTAL ENERGY COSTS $684,530
RECOMMENDED SAVINGS* $323,320 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Fuel Oil #1 Electricity Usage Electricity Demand Fuel Oil #1
$ kWh $ kW-months/year $ MMBtu
01: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$147
Cost:
-
$147 2,820 - - - - $147
2,820
kWh
-
-
kW-months/year
-
-
MMBtu
02: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$34,017
Cost:
$458,990
$34,017 654,172 - - - - $34,017
654,172
kWh
-
-
kW-months/year
-
-
MMBtu
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$272
Cost:
$2,237
$272 5,235 - - - - $272
5,235
kWh
-
-
kW-months/year
-
-
MMBtu
04: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT Savings:
$288,884
Cost:
$300,000
$(-179,712) (-3,465,000) $(-5,164) (-400) $473,760 19,787 $(-179,712)
(-3,465,000)
kWh
$(-5,164)
(-400)
kW-months/year
$473,760
19,787
MMBtu
TOTAL RECOMMENDED Savings:
$323,320
Cost:
$761,227
$(-145,276) (-2,802,774) $(-5,164) (-400) $473,760 19,787 $(-145,276)
(-2,802,774)
kWh
$(-5,164)
(-400)
kW-months/year
$473,760
19,787
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Fuel Oil #1 Electricity Usage Electricity Demand Fuel Oil #1