Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Michigan State University |
---|---|
Assessment Year | 2024 |
Principal Product | Nickel concentrates and copper concentrates |
NAICS | 212234 - Copper Ore and Nickel Ore Mining |
SIC | 1081 - Metal Mining Services |
Sales | $100,000,000-$500,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 55,000 |
Annual Production | 95,000 Tons |
Production Hrs. Annual | 8,760 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $2,092,066 | 31,231,440 | kWh | $0.07 |
Electricity Demand | $163,762 | 52,377 | kW-months/year | $3.13 |
Electricity Fees | $334,791 | - | $ | - |
Fuel Oil #1 | $288,149 | 20,676 | MMBtu | $13.94 |
TOTAL ENERGY COSTS | $2,878,768 | |||
RECOMMENDED SAVINGS* | $48,379 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Fuel Oil #1 | Electricity Usage | Electricity Demand | Electricity Fees | Fuel Oil #1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $15,133 Cost: - |
$14,260 | 203,711 | $874 | 279 | - | - | - | - |
$14,260 203,711 kWh |
$874 279 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $337 Cost: $17 |
$318 | 4,536 | $19 | 6 | - | - | - | - |
$318 4,536 kWh |
$19 6 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $508 Cost: $1,752 |
$478 | 6,823 | $31 | 10 | - | - | - | - |
$478 6,823 kWh |
$31 10 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES |
Savings: $150 Cost: $400 |
$141 | 2,015 | $9 | 3 | - | - | - | - |
$141 2,015 kWh |
$9 3 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,186 Cost: - |
$1,157 | 16,533 | $29 | 9 | - | - | - | - |
$1,157 16,533 kWh |
$29 9 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $84 Cost: $225 |
$79 | 1,135 | $5 | 2 | - | - | - | - |
$79 1,135 kWh |
$5 2 kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $6,376 Cost: $10,087 |
$(-541) | (-7,726) | - | - | - | - | $6,917 | 496 |
$(-541) (-7,726) kWh |
- - kW-months/year |
- - $ |
$6,917 496 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $14,663 Cost: $5,697 |
$(-521) | (-7,446) | $(-180) | (-58) | - | - | $15,365 | 1,102 |
$(-521) (-7,446) kWh |
$(-180) (-58) kW-months/year |
- - $ |
$15,365 1,102 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $9,940 Cost: - |
- | - | - | - | $9,940 | - | - | - |
- - kWh |
- - kW-months/year |
$9,940 - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $48,379 Cost: $18,178 |
$15,371 | 219,581 | $786 | 251 | $9,940 | - | $22,282 | 1,598 | $15,371 219,581 kWh |
$786 251 kW-months/year |
$9,940 - $ |
$22,282 1,598 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Fuel Oil #1 | Electricity Usage | Electricity Demand | Electricity Fees | Fuel Oil #1 |