Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2014 |
Principal Product | fasteners, machined parts |
NAICS | 332721 - Precision Turned Product Manufacturing |
SIC | 3452 - Bolts, Nuts, Rivets, And Washers |
Sales | $10,000,000-$50,000,000 |
# of Employees | 36 |
Plant Area (Sq.Ft.) | 59,000 |
Annual Production | 6,000,000 Pieces |
Production Hrs. Annual | 4,600 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $101,476 | 1,373,400 | kWh | $0.07 |
Electricity Demand | $13,550 | 5,023 | kW-months/year | $2.70 |
Natural Gas | $83,367 | 8,757 | MMBtu | $9.52 |
TOTAL ENERGY COSTS | $198,393 | |||
RECOMMENDED SAVINGS* | $13,362 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $915 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $871 Cost: $620 |
- | - | $871 | 91 |
- - kWh |
$871 91 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $557 Cost: $1,075 |
- | - | $557 | 58 |
- - kWh |
$557 58 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $8,006 Cost: $15,000 |
- | - | $8,006 | 841 |
- - kWh |
$8,006 841 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $3,570 Cost: - |
- | - | $3,570 | 375 |
- - kWh |
$3,570 375 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $358 Cost: - |
$358 | 4,844 | - | - |
$358 4,844 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $13,362 Cost: $16,695 |
$358 | 4,844 | $13,004 | 1,365 | $358 4,844 kWh |
$13,004 1,365 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $915 Cost: $1,075 |
$358 | 4,844 | $557 | 58 | $358 4,844 kWh |
$557 58 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |