IAC logo
IAC Assessment: MZ0170
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MZ0170
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri-Columbia
Assessment Year 2015
Principal Product Flight simulator
NAICS 334511 - Search, Detection, Navigation, Guidance, Aeronautical, and Nautical System and Instrument Manufactur
SIC 3721 - Aircraft
Sales $50,000,000-$100,000,000
# of Employees 225
Plant Area (Sq.Ft.) 140,000
Annual Production 10 Pieces
Production Hrs. Annual 8,760
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $208,120 2,480,569 kWh $0.08
Electricity Demand $14,439 6,528 kW-months/year $2.21
Natural Gas $31,003 4,921 MMBtu $6.30
TOTAL ENERGY COSTS $253,562
RECOMMENDED SAVINGS* $86,387 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT Savings:
$56,753
Cost:
$214,172
$42,420 505,600 $14,333 6,480 - - $42,420
505,600
kWh
$14,333
6,480
kW-months/year
-
-
MMBtu
02: 2.7425 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD Savings:
$4,189
Cost:
$17,018
$4,041 48,159 $148 67 - - $4,041
48,159
kWh
$148
67
kW-months/year
-
-
MMBtu
03: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$14,117
Cost:
-
$7,814 93,137 $299 135 $6,004 953 $7,814
93,137
kWh
$299
135
kW-months/year
$6,004
953
MMBtu
04: 4.512 CONDENSE OPERATION INTO ONE BUILDING Savings:
$11,328
Cost:
-
$8,209 97,845 $504 228 $2,615 415 $8,209
97,845
kWh
$504
228
kW-months/year
$2,615
415
MMBtu
TOTAL RECOMMENDED Savings:
$86,387
Cost:
$231,190
$62,484 744,741 $15,284 6,910 $8,619 1,368 $62,484
744,741
kWh
$15,284
6,910
kW-months/year
$8,619
1,368
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas