IAC Assessment: MZ0190
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MZ0190
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri-Columbia
Assessment Year 2015
Principal Product tires
NAICS 326211 - Tire Manufacturing (except Retreading)
SIC 3011 - Tires And Inner Tubes
Sales $10,000,000-$50,000,000
# of Employees 120
Plant Area (Sq.Ft.) 380,000
Annual Production 325,000 Pieces
Production Hrs. Annual 5,700
Location (State) KS
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $160,475 1,628,592 kWh $0.10
Electricity Demand $70,616 14,120 kW-months/year $5.00
TOTAL ENERGY COSTS $231,091
RECOMMENDED SAVINGS* $86,306 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,483
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost
$ kWh $ kW-months/year $ $
01: 2.2314 REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT Savings:
$36,633
Cost:
$120,000
$35,553 360,810 $1,080 216 - - $35,553
360,810
kWh
$1,080
216
kW-months/year
-
-
$
02: 4.512 CONDENSE OPERATION INTO ONE BUILDING Savings:
$12,608
Cost:
-
$11,393 115,625 $1,215 243 - - $11,393
115,625
kWh
$1,215
243
kW-months/year
-
-
$
03: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS Savings:
$20,868
Cost:
$40,000
$17,027 172,800 $3,201 640 $640 - $17,027
172,800
kWh
$3,201
640
kW-months/year
$640
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,095
Cost:
$3,500
$1,895 19,236 $200 40 - - $1,895
19,236
kWh
$200
40
kW-months/year
-
-
$
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$3,663
Cost:
$1,500
$3,663 37,220 - - - - $3,663
37,220
kWh
-
-
kW-months/year
-
-
$
06: 3.1161 ELIMINATE/REDUCE AN OPERATION Savings:
$928
Cost:
-
$838 8,504 $90 18 - - $838
8,504
kWh
$90
18
kW-months/year
-
-
$
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,483
Cost:
$860
$3,148 31,945 $335 67 - - $3,148
31,945
kWh
$335
67
kW-months/year
-
-
$
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$6,028
Cost:
$1,500
$6,028 61,172 - - - - $6,028
61,172
kWh
-
-
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$86,306
Cost:
$167,360
$79,545 807,312 $6,121 1,224 $640 - $79,545
807,312
kWh
$6,121
1,224
kW-months/year
$640
-
$
TOTAL IMPLEMENTED Savings:
$3,483
Cost:
$860
$3,148 31,945 $335 67 - - $3,148
31,945
kWh
$335
67
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Ancillary Material Cost Electricity Usage Electricity Demand Ancillary Material Cost