Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2019 |
Principal Product | treated mucicipal wastewater |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | <$500,000 |
# of Employees | 4 |
Plant Area (Sq.Ft.) | 348,480 |
Annual Production | 3,760 Units |
Production Hrs. Annual | 8,760 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $240,765 | 3,238,700 | kWh | $0.07 |
Electricity Demand | $21,980 | 5,941 | kW-months/year | $3.70 |
Natural Gas | $15,440 | 1,982 | MMBtu | $7.79 |
TOTAL ENERGY COSTS | $278,184 | |||
RECOMMENDED SAVINGS* | $132,480 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,320 Cost: $320 |
$2,172 | 29,354 | $148 | 40 | - | - |
$2,172 29,354 kWh |
$148 40 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.212 ADOPT IN-HOUSE MATERIAL GENERATION |
Savings: $14,280 Cost: $43,150 |
- | - | - | - | $14,280 | - |
- - kWh |
- - kW-months/year |
$14,280 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $36 Cost: $20 |
$34 | 456 | $2 | 1 | - | - |
$34 456 kWh |
$2 1 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $221 Cost: $1,096 |
$221 | 2,983 | - | - | - | - |
$221 2,983 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $74,880 Cost: - |
- | - | - | - | $74,880 | - |
- - kWh |
- - kW-months/year |
$74,880 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $40,743 Cost: $12,366 |
$35,834 | 484,241 | $4,909 | 1,327 | - | - |
$35,834 484,241 kWh |
$4,909 1,327 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $132,480 Cost: $56,952 |
$38,261 | 517,034 | $5,059 | 1,368 | $89,160 | - | $38,261 517,034 kWh |
$5,059 1,368 kW-months/year |
$89,160 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | One-time Revenue or Avoided Cost |