Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Missouri-Columbia |
---|---|
Assessment Year | 2025 |
Principal Product | fabricated structural steel |
NAICS | 332312 - Fabricated Structural Metal Manufacturing |
SIC | 3441 - Fabricated Structural Metal |
Sales | $50,000,000-$100,000,000 |
# of Employees | 170 |
Plant Area (Sq.Ft.) | 328,000 |
Annual Production | 12,000 Tons |
Production Hrs. Annual | 4,500 |
Location (State) | MO |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $276,008 | 2,524,398 | kWh | $0.11 |
Electricity Demand | $39,435 | 12,814 | kW-months/year | $3.08 |
Natural Gas | $21,834 | 3,934 | MMBtu | $5.55 |
TOTAL ENERGY COSTS | $337,277 | |||
RECOMMENDED SAVINGS* | $476,962 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $19,447 Cost: $22,100 |
- | - | - | - | $19,447 | 3,504 | - | - |
- - kWh |
- - kW-months/year |
$19,447 3,504 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,208 Cost: $400 |
$2,053 | 18,832 | $155 | 50 | - | - | - | - |
$2,053 18,832 kWh |
$155 50 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,090 Cost: $1,405 |
$1,090 | 10,000 | - | - | - | - | - | - |
$1,090 10,000 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $12,542 Cost: $13,100 |
$12,542 | 115,066 | - | - | - | - | - | - |
$12,542 115,066 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $295 Cost: $2,100 |
$295 | 2,705 | - | - | - | - | - | - |
$295 2,705 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $4,865 Cost: - |
$3,084 | 28,296 | - | - | $1,781 | 321 | - | - |
$3,084 28,296 kWh |
- - kW-months/year |
$1,781 321 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $34,746 Cost: $214,502 |
$33,527 | 307,589 | $1,219 | 396 | - | - | - | - |
$33,527 307,589 kWh |
$1,219 396 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $7,435 Cost: $12,750 |
$6,357 | 58,320 | $1,078 | 350 | - | - | - | - |
$6,357 58,320 kWh |
$1,078 350 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $394,334 Cost: $2,410,000 |
$6,334 | 58,114 | - | - | - | - | $388,000 | - |
$6,334 58,114 kWh |
- - kW-months/year |
- - MMBtu |
$388,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $476,962 Cost: $2,676,357 |
$65,282 | 598,922 | $2,452 | 796 | $21,228 | 3,825 | $388,000 | - | $65,282 598,922 kWh |
$2,452 796 kW-months/year |
$21,228 3,825 MMBtu |
$388,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||