IAC logo
IAC Assessment: MZ1010
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: MZ1010
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Missouri-Columbia
Assessment Year 2024
Principal Product police station
NAICS 922120 - Police Protection
SIC 6221 - Commodity Contracts Brokers, Dealers
Sales <$500,000
# of Employees 55
Plant Area (Sq.Ft.) 23,904
Annual Production 1 Pieces
Production Hrs. Annual 3,120
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $45,715 385,440 kWh $0.12
Natural Gas $9,274 673 MMBtu $13.78
TOTAL ENERGY COSTS $54,989
RECOMMENDED SAVINGS* $14,080 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Usage
$ kWh
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY Savings:
$13,002
Cost:
$76,245
$13,002 109,626 $13,002
109,626
kWh
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$498
Cost:
$380
$498 4,193 $498
4,193
kWh
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$580
Cost:
$404
$580 4,886 $580
4,886
kWh
TOTAL RECOMMENDED Savings:
$14,080
Cost:
$77,029
$14,080 118,705 $14,080
118,705
kWh
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - -
-
kWh
Savings
Cost
$ kWh
Electricity Usage Electricity Usage