Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1998 |
Principal Product | Plastic Foam Products |
NAICS | n/a |
SIC | 3086 - Plastics Foam Products |
Sales | $1,000,000-$5,000,000 |
# of Employees | 18 |
Plant Area (Sq.Ft.) | 40,000 |
Annual Production | 25,000,000 Units |
Production Hrs. Annual | 5,473 |
Location (State) | NV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $7,127 | 169,109 | kWh | $0.04 |
Electricity Demand | $7,981 | 860 | kW-months/year | $9.28 |
Electricity Fees | $914 | - | $ | - |
Natural Gas | $26,375 | 5,082 | MMBtu | $5.19 |
TOTAL ENERGY COSTS | $42,397 | |||
RECOMMENDED SAVINGS* | $68,776 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,094 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes | Primary Product | Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $166 Cost: $200 |
$163 | 3,810 | $3 | - | - | - | - | - | - | - |
$163 3,810 kWh |
$3 - $ |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $87 Cost: $74 |
$85 | 2,052 | $2 | - | - | - | - | - | - | - |
$85 2,052 kWh |
$2 - $ |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $234 Cost: $50 |
$229 | 5,569 | $5 | - | - | - | - | - | - | - |
$229 5,569 kWh |
$5 - $ |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1133 ADJUST BURNERS FOR EFFICIENT OPERATION |
Savings: $341 Cost: $600 |
- | - | - | - | $341 | 66 | - | - | - | - |
- - kWh |
- - $ |
$341 66 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $337 Cost: $255 |
- | - | - | - | $337 | 65 | - | - | - | - |
- - kWh |
- - $ |
$337 65 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $51,111 Cost: $60,000 |
- | - | - | - | - | - | - | - | $51,111 | - |
- - kWh |
- - $ |
- - MMBtu |
- - $ |
$51,111 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $16,500 Cost: $66,275 |
- | - | - | - | - | - | $16,500 | - | - | - |
- - kWh |
- - $ |
- - MMBtu |
$16,500 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $68,776 Cost: $127,454 |
$477 | 11,431 | $10 | - | $678 | 131 | $16,500 | - | $51,111 | - | $477 11,431 kWh |
$10 - $ |
$678 131 MMBtu |
$16,500 - $ |
$51,111 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,094 Cost: $67,149 |
$248 | 5,862 | $5 | - | $341 | 66 | $16,500 | - | - | - | $248 5,862 kWh |
$5 - $ |
$341 66 MMBtu |
$16,500 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes | Primary Product | Electricity Usage | Electricity Fees | Natural Gas | Administrative Changes | Primary Product |