Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Old Dominion Univ. |
---|---|
Assessment Year | 2000 |
Principal Product | Converted paper products |
NAICS | n/a |
SIC | 2679 - Converted Paper Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 115 |
Plant Area (Sq.Ft.) | 152,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 2,340 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $42,222 | 766,413 | kWh | $0.06 |
Electricity Demand | $15,926 | - | kW-months/year | - |
Electricity Fees | $1,729 | - | $ | - |
Natural Gas | $45,943 | 11,476 | MMBtu | $4.00 |
TOTAL ENERGY COSTS | $105,820 | |||
RECOMMENDED SAVINGS* | $10,593 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Natural Gas | Administrative Changes | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,365 Cost: $5,892 |
$2,365 | 735 | - | - |
$2,365 735 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $3,900 Cost: $3,000 |
- | - | $3,900 | - |
- - MMBtu |
$3,900 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,027 Cost: $1,500 |
$1,027 | 319 | - | - |
$1,027 319 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $1,013 Cost: $1,360 |
$1,013 | 315 | - | - |
$1,013 315 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $2,084 Cost: $700 |
$2,084 | 647 | - | - |
$2,084 647 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $204 Cost: - |
- | - | $204 | - |
- - MMBtu |
$204 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,593 Cost: $12,452 |
$6,489 | 2,016 | $4,104 | - | $6,489 2,016 MMBtu |
$4,104 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Natural Gas | Administrative Changes | Natural Gas | Administrative Changes |