Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2001 |
Principal Product | Asphalt |
NAICS | n/a |
SIC | 2834 - Pharmaceutical Preparations |
Sales | $5,000,000-$10,000,000 |
# of Employees | 15 |
Plant Area (Sq.Ft.) | 400,000 |
Annual Production | 200,000 Tons |
Production Hrs. Annual | 2,340 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $69,499 | 946,261 | kWh | $0.07 |
Electricity Fees | $2,063 | - | $ | - |
Natural Gas | $358,603 | 101,671 | MMBtu | $3.53 |
TOTAL ENERGY COSTS | $431,593 | |||
RECOMMENDED SAVINGS* | $52,505 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $658 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Personnel Changes | Increase in Production | Electricity Usage | Natural Gas | Personnel Changes | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $335 Cost: $304 |
$335 | 4,563 | - | - | - | - | - | - |
$335 4,563 kWh |
- - MMBtu |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $323 Cost: $439 |
- | - | $323 | 75 | - | - | - | - |
- - kWh |
$323 75 MMBtu |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES |
Savings: $17,946 Cost: $30,145 |
- | - | $17,946 | 4,171 | - | - | - | - |
- - kWh |
$17,946 4,171 MMBtu |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $409 Cost: $354 |
$409 | 5,576 | - | - | - | - | - | - |
$409 5,576 kWh |
- - MMBtu |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $8,337 Cost: $9,259 |
$8,337 | 113,579 | - | - | - | - | - | - |
$8,337 113,579 kWh |
- - MMBtu |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT |
Savings: $1,170 Cost: $1,000 |
- | - | - | - | $1,170 | - | - | - |
- - kWh |
- - MMBtu |
$1,170 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $23,985 Cost: $27,632 |
- | - | $2,385 | 554 | - | - | $21,600 | - |
- - kWh |
$2,385 554 MMBtu |
- - $ |
$21,600 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $52,505 Cost: $69,133 |
$9,081 | 123,718 | $20,654 | 4,800 | $1,170 | - | $21,600 | - | $9,081 123,718 kWh |
$20,654 4,800 MMBtu |
$1,170 - $ |
$21,600 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $658 Cost: $743 |
$335 | 4,563 | $323 | 75 | - | - | - | - | $335 4,563 kWh |
$323 75 MMBtu |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Personnel Changes | Increase in Production | Electricity Usage | Natural Gas | Personnel Changes | Increase in Production |