Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2001 |
Principal Product | Winches |
NAICS | n/a |
SIC | 3531 - Construction Machinery |
Sales | $10,000,000-$50,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 91,000 |
Annual Production | 9,600 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $127,401 | 2,432,320 | kWh | $0.05 |
Electricity Fees | $2,969 | - | $ | - |
Natural Gas | $10,811 | 2,134 | MMBtu | $5.07 |
TOTAL ENERGY COSTS | $209,453 | |||
RECOMMENDED SAVINGS* | $344,259 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $140,111 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $2,978 Cost: $130 |
$2,978 | 70,400 | - | - | - | - | - | - |
$2,978 70,400 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS |
Savings: $4,484 Cost: $255 |
$4,484 | 106,808 | - | - | - | - | - | - |
$4,484 106,808 kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,627 Cost: $240 |
$3,867 | 91,420 | $760 | 15 | - | - | - | - |
$3,867 91,420 kWh |
$760 15 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $1,170 Cost: $50,000 |
- | - | - | - | $1,170 | - | - | - |
- - kWh |
- - kW-months/year |
$1,170 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $131,000 Cost: $92,000 |
- | - | - | - | - | - | $131,000 | - |
- - kWh |
- - kW-months/year |
- - lb |
$131,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.445 INSTALL EQUIPMENT TO MOVE PRODUCT |
Savings: $200,000 Cost: $200,000 |
- | - | - | - | - | - | $200,000 | - |
- - kWh |
- - kW-months/year |
- - lb |
$200,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $344,259 Cost: $342,625 |
$11,329 | 268,628 | $760 | 15 | $1,170 | - | $331,000 | - | $11,329 268,628 kWh |
$760 15 kW-months/year |
$1,170 - lb |
$331,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $140,111 Cost: $92,495 |
$8,351 | 198,228 | $760 | 15 | - | - | $131,000 | - | $8,351 198,228 kWh |
$760 15 kW-months/year |
- - lb |
$131,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes |