Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2004 |
Principal Product | Carbonated Beverages |
NAICS | 312111 - Soft Drink Manufacturing |
SIC | 2086 - Bottled And Canned Soft Drinks |
Sales | $100,000,000-$500,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 17,000,000 Pieces |
Production Hrs. Annual | 5,200 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $266,155 | 10,719,100 | kWh | $0.02 |
Electricity Demand | $155,233 | 25,827 | kW-months/year | $6.01 |
Electricity Fees | $(-10,980) | - | $ | - |
Natural Gas | $103,243 | 26,380 | MMBtu | $3.91 |
TOTAL ENERGY COSTS | $513,651 | |||
RECOMMENDED SAVINGS* | $68,843 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $32,832 Cost: $29,700 |
- | - | - | - | $32,832 | 8,389 | - | - |
- - kWh |
- - kW-months/year |
$32,832 8,389 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,754 Cost: $11,650 |
$4,754 | 124,134 | - | - | - | - | - | - |
$4,754 124,134 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $6,784 Cost: $11,990 |
- | - | - | - | $6,784 | 1,733 | - | - |
- - kWh |
- - kW-months/year |
$6,784 1,733 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,056 Cost: $656 |
$1,318 | 53,165 | $738 | 123 | - | - | - | - |
$1,318 53,165 kWh |
$738 123 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,502 Cost: - |
$2,502 | 65,334 | - | - | - | - | - | - |
$2,502 65,334 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,158 Cost: $5,157 |
$3,041 | 122,626 | $117 | 19 | - | - | - | - |
$3,041 122,626 kWh |
$117 19 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $1,565 Cost: $789 |
- | - | - | - | $1,565 | 400 | - | - |
- - kWh |
- - kW-months/year |
$1,565 400 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $15,192 Cost: $655 |
$9,926 | 400,241 | $5,554 | 924 | - | - | $(-288) | - |
$9,926 400,241 kWh |
$5,554 924 kW-months/year |
- - MMBtu |
$(-288) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $68,843 Cost: $60,597 |
$21,541 | 765,500 | $6,409 | 1,066 | $41,181 | 10,522 | $(-288) | - | $21,541 765,500 kWh |
$6,409 1,066 kW-months/year |
$41,181 10,522 MMBtu |
$(-288) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |