Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2008 |
Principal Product | Above ground storage tanks |
NAICS | 332313 - Plate Work Manufacturing |
SIC | 3443 - Fabricated Plate Work (boiler Shops) |
Sales | $100,000,000-$500,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 130,000 |
Annual Production | 70 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $216,737 | 3,156,300 | kWh | $0.07 |
Natural Gas | $56,663 | 7,794 | MMBtu | $7.27 |
TOTAL ENERGY COSTS | $273,400 | |||
RECOMMENDED SAVINGS* | $25,306 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,306 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $2,213 Cost: - |
$2,213 | 36,305 | - | - |
$2,213 36,305 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $14,263 Cost: $4,638 |
- | - | $14,263 | 1,962 |
- - kWh |
$14,263 1,962 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $525 Cost: $2,871 |
$525 | 7,614 | - | - |
$525 7,614 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $3,105 Cost: $1,908 |
- | - | $3,105 | 427 |
- - kWh |
$3,105 427 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $5,200 Cost: - |
$5,200 | - | - | - |
$5,200 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,306 Cost: $9,417 |
$7,938 | 43,919 | $17,368 | 2,389 | $7,938 43,919 kWh |
$17,368 2,389 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,306 Cost: $9,417 |
$7,938 | 43,919 | $17,368 | 2,389 | $7,938 43,919 kWh |
$17,368 2,389 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |